Before a planned shutdown, compare two dates for each critical steam asset: when production needs it back and when a compatible replacement could actually be fitted. A part can be in stock and still miss the restart if it needs a different connection, testing or specialist labour. The difference between those dates tells maintenance and procurement where to focus their review.

Decide which failures would threaten the restart

Begin with the equipment the process depends on. Include assets where failure would interrupt production, prevent the plant from restarting safely or affect product quality. Record whether an approved standby can carry the required load and how long the site can operate without the asset. The same type of valve can have different stocking priorities on two lines if only one has standby capacity.

Use three questions to review each item. What happens if it fails? How long can the process wait? How long will it take to identify, source, fit and verify a compatible replacement? A long lead time matters most where the site has little time to recover.

Maintenance technician working beside industrial steam pipework
Use the shutdown review to check the parts list against the equipment installed on site.

Match the spare to the installed equipment

EquipmentWhat to verify before ordering
Steam trapsConfirm the trap type, connection and operating conditions. Check the manufacturer’s instructions for serviceable parts and whether a complete replacement is needed. Use the steam trap testing and maintenance guide to inform that review.
Control valvesUse the asset tag and nameplate to identify the body, trim and actuator configuration. Check the applicable documentation in the control valve range before treating a repair kit or actuator as interchangeable.
Boiler controls and condensate equipmentConfirm the installed model and the manufacturer’s instructions. Record any commissioning or functional checks needed before the equipment can return to service.

Make the list usable during a shutdown

Give each line in the spares list enough detail for the next shift to act on it. Include the asset tag, approved part number, quantity on hand, storage location, supplier and the date the lead time was last confirmed. Mark stock allocated to planned jobs so the team can see what remains available for an unexpected repair.

Review used parts and any items taken from stores after each shutdown. Update the list when the installed equipment changes, then confirm who will replenish the stock. If the review finds repeat failures or a difficult replacement, use the next steam system repairs and maintenance review to decide whether to address the underlying fault and revise the spares plan.

Read the Spirax Sarco UK news article on critical spares for the background to this checklist.